|

|
Allen's foremen, Darin Stroud and Jesse Garcia,
made quick work of getting accustomed to the difficult working environment
and Underground finished the cable tray installation n ahead of schedule.
Once the tray was completed,
Superintendent Chris Stream came to help install the 22,000 feet of fiber
optic cable. In just three short nights, Underground crews completed the
cable pull and had done what had never been done before; installed the longest
run of 432 strand ribbon cable that the manufacturer had ever produced.
Not only was the fiber optic cable record setting, but the fiberglass cable
tray manufacturer had never produced a single run of cable tray this long
ever before.
Underground has a lot to be proud of on this project. We completed a
quality project that the owner is extremely happy with and we built it ahead
of schedule and under budget. We look forward to many more challenging projects
like this with SBC and BART in the future.
|
Every so often, Underground is fortunate to come across a truly unique
project. This summer, SBC awarded Underground a project to install 19,300
feet of 24 inch wide fiberglass cable tray in the BART Transbay tunnel from
Oakland to San Francisco. The project required drilling into the upper gallery's
concrete walls between the two BART tracks and installing brackets every
ten feet with epoxied studs. Also, the tube was built in pre-manufactured
sections and sunk into place with barges back in the 1960s. Each concrete
section is about 350 feet long and has a steel joint connecting one to the
other. At these 57 tube joints, we welded stainless steel brackets onto
the joint walls. Then, after all the brackets were installed, we assembled
and installed the entire cable tray and placed on the brackets. While all
this work sounds rather simplistic, access to the site was anything but
that.
Working in a tunnel underneath the bay required a great deal of coordination.
All of the materials had to be brought in on a BART work train from Oakland. |

The only times we could run the work train so that it would not interfere with BART's normal operating hours was on the weekends,
at night. Furthermore, in the BART gallery between the tracks, the hatches
from the lower gallery to the upper gallery are spaced about 1,000 feet
apart. Therefore, we had to stage all of our materials at the hatches in
the lower gallery every 1,000 feet and distribute it throughout the upper
gallery by hand. Additionally, in order to work in the upper gallery, we
had to have BART safety monitors in the upper and lower galleries at all
times for our protection. Throw in performing all the work at night and
we had a tough job of planning the project.
Underground assigned Superintendent Allen Ellison to run this complex
project. With years of airport work under his belt, Allen quickly adapted
to the new working restrictions and created a great working relationship
with both SBC and BART. |