PROJECT PROFILES

Joint Trench
El Dorado Hills, CA
by Dan Harvey




  Underground Construction Co., Inc. has recently completed a joint trench project for SBC and Comcast in November 2003. The job consisted of approximately one and a half miles of installation of under ground facilities to enable above ground lines to be removed.

The majority of the work was on the highly congested Green Valley Road. Work hours were restricted to six hours a day. By the time traffic control was set up and trenching operations began, it was time for us to clean up and be off the road by 3:00 pm.

The crew placed approximately 28,000 feet of different size ducts, 30 manholes and vaults ranging in size from 17 x 30 inches to 5 x 10 feet. The crew developed a close working relationship with the El Dorado County Department of Transportation, since the project was constructed in and along a road in their jurisdiction. Future plans to widen the road and construct sidewalks required strict control during construction. It has been a challenging project, to say the least.

The project was under the watchful eyes of Project Manager Dan Harvey and Superintendent Bob Roberts. The original

foremen on this project were Jesus Ochoa and William Smith (Smitty). Jesus was later transferred to another project and Foreman Jose Lopez-Ceja took over. While Smitty had taken care of setting all the boxes, pads, and working on laterals, Jesus and then Jose placed the entire main line trench.

In addition to all the work going on, we hired a number of new employees for this project. This meant that along with completing the project in a safe and timely manner, Bob, Smitty, Jesus and Jose were also busy teaching the new employees as they went. It has been a positive learning experience for all involved.


Stanford University - Communications Department
by Dan Harvey

  In August 2003, Underground Construction Co., Inc. successfully completed a project for the Stanford University Communications Department. The project consisted of placing a communication duct structure, which varied in size from 8 to 28 conduits. Hydraulic shoring was necessary throughout the entire project due to the 8-foot trench depth.

The crew also placed four special ordered vaults for this project with the largest one measuring approximately 13 feet wide by 13 feet long by 17 feet deep. We used sheeting and hydraulic walers for the large vault, while using hydraulic shoring and end panels for the other vaults. The sizes of the other vaults were 6 feet wide by 15 feet long by 9 feet deep.

Although this project was located in a heavily traveled work site, we thank the construction team of Project Manager Dan Harvey, Superintendent George Castro, and Foreman Jesus Ochoa for a job done safety and on schedule.




Back to Top of Page