PROJECT PROFILES

UC Merced Site Development and
Infrastructure Project
by Ashley Carter




  Underground Construction Co., Inc. has recently completed the UC Merced Site Development and Infrastructure project. This project is the first phase of the building of the University of California's newest campus located in Merced, California. Underground's portion of the work was the installation of the electrical and communication infrastructure to support the new university. The project was comprised of 20,000 feet of trench and 86 manholes.

In a little less than three months, our crew installed 10,000 feet of communication trench, which included a joint duct bank consisting of a local exchange carrier and an information technology network.

Both the electrical and communication trenches were encased in concrete with rebar reinforcement. The conduit duct

banks included duct spacers to maintain the appropriate separation and tied down to

prevent floating during the encasement installation. The trenches were backfilled with native material. The crew placed 55 communication manholes to accommodate the two lines.


The manholes were placed in pairs to facilitate the segregation between the two lines. Also installed were 10,000 feet of electrical duct bank and 31 large electrical vaults. The size of these manholes was 15 feet long by 4 feet wide by 11 feet deep, similar to the installation of a small C.E.V. (Controlled Environmental Vault).

Though the site was unimproved prior to the beginning of the project, it quickly posed many challenges for our crew.

Working among the other contractors installing the wet utility infrastructure, ongoing site work, and the construction of the new campus buildings caused logistical challenges for our crew. Underground also was required to install trenches and manholes to a depth of 20 feet to allow for proper cover required to bore under irrigation canals. Unanticipated ground water was also encountered at various locations.

Project Manager Ashley Carter, Project Superintendent Rich Swanson, Foremen Gustavo Elias-Cortes, Arturo Navarro and Mike Moser led our project team. This group supervised a crew of nearly 30 employees with great success. A big thanks goes out to them and their crew for completing the project safely and on schedule during the peak of the high summer temperatures.

 EMPLOYEE SPOTLIGHT


Tom Thornton
by Matt Cook

  The year was 1973. President Nixon was engulfed by the Watergate Scandal. Bad, Bad Leroy Brown, by Jim Croce, was the #1 song on the radio. And Tom Thornton came to work for Underground Construction. Tom Thornton started working as an auto mechanic after Henry Haberman came to work for Underground as the shop foreman, and convinced Tom that it was a great place to work. In three short years, Henry left for a project in Atlanta, and Tom replaced him as the shop foreman. Tom, having previously only worked on trucks, studied hard to learn more about equipment. In 1983, he became the Equipment Division Manager in charge of the maintenance and purchasing for the entire company. At that time, Tom was calculating all of his equipment rates with a pencil, paper and calculator.  
Since then, a lot has changed around Underground. Paper and pencil has given way to personal computers, but Tom is still running the equipment division efficiently, and effectively. His most notable thought of Underground is the "can-do" attitude that has been so pervasive throughout the

company over the years. He has always been proud of the diverse and intricate projects that Underground has tackled over the years, from the cable car restoration project in San Francisco to the Feather River Canyon project. Tom also remarks how Underground has always employed the highest caliber of employees, has always been on the cutting edge of technology, and has one of the best shop facilities in the industry. There are few contractors that provide a more safe, clean and well-equipped shop than Underground.

On his personal time, Tom enjoys skiing, golf and cooking. Tom lives in Alamo with his wife, Amelia, and has two stepchildren, Kristin, 21, and Nick, 17. We look forward to many more years with Tom.




Back to Top of Page