PROJECT PROFILE

STANFORD/PORTLAND INTERNATIONAL
YANKEE HILL
by Ben Lyon, Matt Cook, Tim Richards

Stanford Work Continues
by Ben Lyon

Underground Construction has worked with the Stanford University Utilities Division for several years and on various projects. Traditionally, work at Stanford University has been scheduled during the summer and winter breaks. This past summer we were, once again, awarded a steam system replacement project. The Mirrieless House/Galvez Mall Project was completed in August under the watchful eyes of Project Manager Ben Lyon, Superintendents Bob Roberts and Jeff Smith, and Foreman Jose Ceja. The project consisted of proving a route, and then placing welded steel condensate return lines and manholes to provide steam service to the dormitories on campus. Although it sounds simple, the schedule, working hours, hot conditions and working with students and the faculty made it a real challenge. Our crews embraced the project and completed it ahead of schedule.

Recently, Underground was awarded a contract for the Chem/Bio Project. Superintendent Joe Tagliaboschi, Foremen Darrin Stroud and William Smith, along with their crews, have just started the steam project that includes an addition to an existing manhole, placing a new manhole, placing pre-cast utility corridors, and the steam lines to a building that is currently under construction.

With a tight schedule, inclement weather, and a congested work site, the Chem/Bio Project is also going to be a challenge that we are looking forward to completing before the start of school in late January.

Portland International Airport
by Matt Cook

After completing the first phase of the Terminal C expansion project at Portland International Airport in December of 1997, Underground Construction returned to complete the third and final phase of the airport expansion, which proved to be the toughest yet. Not only do the crews have to deal with airport security issues in a post-September 11th world, but the confined work area had two other contractors and extensive plumes of contamination, making the work all the more difficult.

Underground left nothing to chance and sent our "A-Team" to perform the work. Superintendents Allen Ellison and Chris Stream, along with Foreman Greg McNeilly, arrived in Portland in late April to drain, abandon and grout inject the existing fuel lines. Then we had to wait until late June to send Superintendent Joe Kovacich and Greg back to the City of Roses to begin construction on the new fuel system. They installed 1,100 feet of new 12" and 14" fuel mains, 700 feet of 6" fuel laterals, thirteen hydrant pits and three vent pits in less than two months. The crew completed the work ahead of schedule with no adverse impacts to airport operations.





 Yankee Hill Road Project

Excavation and backfill of an 18î diameter ductile iron sanitary sewer for the South Placer Municipal Utility District. This 18î pipeline crossed the Union Pacific Railroad utilizing three cased bores and included a casing suspended across the Middle Antelope Creek in Rocklin, CA.



Back to Top of Page